GENSLER ATLANTA OFFICE

Humphries completed this 2nd generation 25,000 square foot build out for Gensler’s Atlanta Headquarters in late 2011. The Project was a LEED fast track project completed in 10 Weeks. The scope of work included the use of multiple ceiling configurations, with exposed ceilings, GWB ceilings and specialty ceiling types throughout. Three different glass systems were used throughout the space including a Dorma folding glass panel system at the main boardroom. Both elevator lobbies were re-built using Reclaimed Heart of Pine flooring on the ceilings, walls and floors. All of the elevator cab doors were reclad in mirrored stainless steel. Mechoshades were used throughout the floor in lieu of building standard blinds. The all custom lighting package and mechoshades were controlled by a custom Crestron control system throughout the space, offering thousands of lighting scene options.

LEED
LEED-CI Platinum

Project Location

Atlanta, GA

Client

Gensler

Architect

Gensler

Project Size

25,000 SF

Completion

2011